The Week Ahead for Friday, January 27, 2012

The elevated concrete deck over the north wing will be poured on Monday. There is a possibility that the north slab on grade will be poured on Thursday.  Both of these pours will require after-hours work to complete.  This has been communicated with the City of Clayton.  Access for both of these pours will be from the east gate on University. Please see the attached letter outlining the anticipated schedule for the remaining concrete pours.  Steel erection west of the commons area and roof decking of both classroom wings will begin this week.  Exterior framing, sheathing and waterproofing will continue on the south classroom wing.  Fireproofing in the basement will also be completed.

WMS