Wydown Today

The Week Ahead for Friday, April 6, 2012

Roofing work will continue over the commons area roof and will be nearing completion by the end of the week.  Brick installation will continue up the south elevation and at both elevations between the classroom wings.  An additional crew will start mid-week to begin installing brick on the north elevation.  Inside the building, drywall will continue on the first floor of both classroom wings.  Overhead mechanical/electrical rough-in will continue on the second floor of both wings and at the first floor commons area.  Interior wall framing will begin on the south wing second floor and fireproofing will take place on the second floor of the commons and west end.