propS

Clayton High School

Total Budget - $37.7 million
Renovations and Additions - $28.32 million
Building Infrastructure - $3.34 million
Athletic/Stuber Addition/Renovation - $3.11 million
Theater Sound, Lights and Staging Renovation - $1.80 million
Replace Orange Rooms - $855,000
Field House Lockers/Restrooms - $271,000


Project Start - November 2009
Projects Complete - November 2011
  • Relocated Orange Rooms - March 2010
  • Cottage/Career Ed Building Demo - April 2010
  • Athletic Renovation/Addition - August 2010
  • Science/Technology Building - August 2011
  • Theater and Departmental Renovations - August 2011
  • Ren. of Existing Third-Floor Science Rooms - November 2011
CHS

Project Funded Through Prop S
  • New, three-story science and technology addition replaces outdated science rooms with state of the art science labs and classrooms, designed and sized to meet the latest standards in science education
  • All science labs and classrooms are completely renovated or replaced on the top floor of CHS
  • Cottage and Career Ed building demolished to make room for new addition; both were built as part of the original CHS in 1952 and had seen few significant renovations since then
  • Addition also provides new, relocated learning space for pre-engineering, robotics, journalism, yearbook, world languages and FACS programs
  • Print shop and 8,000 sf of District-wide storage located in basement of addition providing a significant solution to storage issues District-wide
  • Orange Rooms replaced and relocated in courtyard next to Center of Clayton
  • Compact, two-story addition to Stuber Gym relocates athletic offices to improve circulation issues, moves health classrooms into addition to allow for improved team locker areas and renovates training room and other areas to address several Title IX compliance issues
  • English, Social Studies and World Languages department consolidated within building to improve collaboration
  • Some classroom space reconfigured or remodeled to allow for improved flexibility
  • Antiquated sound, lighting and staging equipment in theater/auditorium replaced with new equipment to solve problem of needing to repair existing equipment for which parts are no longer made
  • Additional power and data wiring will be provided to increase capacity in all classrooms
  • HVAC equipment will be updated and replaced to improve indoor air quality and increase energy efficiency
  • Infrastructure updated to increase boiler and chiller capacity
Supporting Materials

PDFClayton High School poster with details on how the renovations and improvements meet the school's needs

PDFClayton High School Plans

PDFClayton High School Cost Estimate