Total Budget - $1.85
million Classroom Addition - $1.32 million Building Infrastructure - $93,000 Site/Parking Improvements - $434,000
Project Start - November 2009 Project Complete - April 2010
Project Funded Through Prop
S
Two-story addition allows for two additional full-day, early childhood classrooms to expand capacity for ECE offerings (when full, the two additional rooms would net approx. $115,00 of additional revenue for the District)
Lower level of addition would be “shell space” and left unfinished in order to have space to accommodate future District or Family Center needs
New elevator provides improved ADA access to entire building
Expanded parking and improved vehicular circulation on upper and lower parking lots to improve safety during pick-up/drop-off and address parking needs