Total Budget - $1.85 million
Classroom Addition - $1.32 million
Building Infrastructure - $93,000
Site/Parking Improvements - $434,000

Project Start - November 2009
Project Complete - April 2010

FC

Project Funded Through Prop S
  • Two-story addition allows for two additional full-day, early childhood classrooms to expand capacity for ECE offerings (when full, the two additional rooms would net approx. $115,00 of additional revenue for the District)
  • Lower level of addition would be “shell space” and left unfinished in order to have space to accommodate future District or Family Center needs
  • New elevator provides improved ADA access to entire building
  • Expanded parking and improved vehicular circulation on upper and lower parking lots to improve safety during pick-up/drop-off and address parking needs